Project
Rades Bridge / La Goulette Lot IV
Route de Liaison Nord Extension of the Voie Express CH.413
- Contract amount: 11,149,304,981 TND
- Work execution time: 24 months
- Client: Ministry of Housing Equipment and Land Use Planning
Consistency of the work
The work carried out in this project includes the construction of:
- North Extension Route (Extension of the Express Route), over a length of 6,000 km.
- 1 Bridge over Khair-eddine Canal.
- 1 STEG canal bridge
- 1 Crossroads
- Drainage works (reinforced concrete channel, single and multiple scuppers)
- Bridge over Khair-eddine Canal: Length of the bridge: 58 ml with 4 spans of 14.50 ml with 2 reinforced concrete decks, the work is based on driven piles of reinforced concrete 25 meters deep
- STEG Canal Bridge: Length of the bridge: 14.5 ml with 2 reinforced concrete decks, the structure is based on driven piles in reinforced concrete 25 meters deep
The main quantities
- Landfill or landfill: 6,000 m3
- Loan for backfill: 185,000 m3
- Gravel bitumen: 26,500 m3
- Bituminous concrete: 7,500 m3
- Concrete: 2,467 m3
- Concrete reinforcement: 350,000 Kg