- Contract amount: 3,336,089,126 TND
- Work execution time: 24 months
- Client: Department of Dams and Major Hydralic Works
- Progress works : 90 %
- Contract amount: 21 702 182.072 TND
- Work completion time: 240 days
- Client: Ministry of Housing Equipment and Regional Planning
Consistency of the work - Progress works : 75 %
- Contract amount: 10 252 081.817 TND
- Work completion time: 300 days
- Client: Ministry of Housing Equipment and Regional Planning
- Progress works : 59 %