- Contract amount: 56,291,150,000 TND
- Work completion time: 1080 days
- Client: Societe du Reseau Ferroviaire Rapide de Tunis
- Progress works : 95 %
- Contract amount: 10 252 081.817 TND
- Work completion time: 300 days
- Client: Ministry of Housing Equipment and Regional Planning
- Progress works : 59 %