Project
Execution works of the reservoir dam in
SAIDA-MANOUBA
- Market amount : 137,944,842,011 TND
- Work execution deadline: 48 months
- Project owner: General Directorate of Dams and Major Hydraulic Works
- Progress of work: 68%
Consistency of the work
Construction of a dam and its associated structures on wadi el MELAH, its reservoir with a total capacity of 45 million m3 over an area of 310 Ha.
- The surface area of the BV is around 7.05km2.
- The dike is of the zoned earth type, its maximum height on TN is 51m, its length at the crest is 1100m and its width at the crest is 8m
- The volume of the dam body is of the order of 3,673,000m3
- The volume of concrete work: 28,000m3, diaphragm wall: 750 ml.
- Piles with a diameter of 800mm and a depth of 30ml: 81U.