Project
Elevation work at 8 crossroads on the KM4 ring road in the governorate of SFAX-Tranche 1-Lot1: Crossroads RL911 & KAYED MOHAMED AND RR81
- Contract amount: 47 345 718.647 TND
- Work execution time: 30 months
- Client: Ministry of Equipment-General Directorate of Bridges and Roads
Consistency of the work
The works to be carried out are: clearing of rights-of-way, earthworks, construction of the layers of roadways and outbuildings, sanitation and drainage, construction of bridges at the RL911 crossroads (continuous slab bridge in BA) and at the Kayed crossroads Mohamed-RR81 (continuous slab bridge in prestressed concrete) as well as geotextile work, development of 3 roundabouts, signage, security, equipment and public lighting.