Rehabilitation works of the GP16 road in the governorate of TOZEUR

Rehabilitation works of the GP16 road in the governorate of TOZEUR

  • Contract amount: 12,509,414.108 TND
  • Work execution time: 22 months
  • Client: General Directorate of Bridges and Roads

    Consistency of the work

    The work is summarized as follows:

    Clearance of rights-of-way;
    Earthworks: excavation in soft and rocky terrain, demolition of roadways and borrowing of materials for backfill;
    Implementation of tuff for the foundation layer, GC 0/20 for base and reinforcement layer, selected backfill under the shoulder, 0/40 quarry waste for the shoulder, an impregnation layer, a two-layer surface plaster, with a bonding layer and a 6 cm thick BB coating;
    Drainage of the roadway and its surroundings;
    Construction of hydraulic structures and transverse drainage structures (culverts, extension of culverts and development of crossroads);
    Signage