- Contract amount: 8 838 894.209 TND
- Work completion time: 600 days
- Client: Department of Dams and Major Hydraulic Works
Consistency of the work
The services covered by the contract include the execution studies, the supply and the execution of the following works:
Masterpieces :
Two works of art: overpass on track X in solid preconstructed concrete slab connecting Ibn Khaldoun Bab Saadoune.
Structural work: overpass on track X in solid preconstructed concrete slab for the left turns Ibn Khaldoun - Ariana.
Structural work: overpass on track X3 in solid reinforced concrete slab to level Romana and track X3.
Pedestrian crossings:
2 pedestrian overpasses
1 pedestrian underpass
Works relating to earthworks, drainage, roads, signage, roadway and railway platform