LOT 2/1 Transp + Pipe laying in Sidi Barrak Sejnane

LOT 2/1 Transp + Pipe laying in Sidi Barrak Sejnane

  • Contract amount: 5,131 909,326 TND
  • Work execution time: 16 months
  • Client: Ministry of Agriculture and Hydraulic Resources
Consistency of the work

The services covered by the contract include the execution studies, the supply and the execution of the following works:

Transport + Earthwork + Installation:

Transport: 18600 M.L, pipe diameter 1800 F.B
Earthwork and laying of 18,600 M.L and diameter 1,800 F.B
Laying in trenches of 15965 M.L
Installation on 2635 M.L support
Civil Engineering: Execution of a 65,000 M.C regulator basin, Sectioning works, 19 U drain works, 19 U suction cup works, Execution of 21 aerial crossings (314 soles, 120 pilons, 190 aprons, 794 cradles)
Wall and Elbow:

Head wall 41 U, Anchor massif 108 U, Restitution work
60 U Vertical Elbow, 35 U Horizontal Elbow