Project
Widening and strengthening of Route MC 59 from KP 23.4 to KP 44.6
in the Governorate of Jendouba Lot n ° 2 CH.430
- Contract amount: 6,785,797,302 TND
- Work completion time: 18 months
- Client: Ministry of Housing Equipment and Land Use Planning
Consistency of the work
This project includes all works to widen and strengthen the MC 59 road over a length of 21.1 km.
- Earthworks
- Pavement
- Sanitation and drainage
- 1 bridge structure with prefabricated beams, and with deep foundations (bored piles Ø 1000).
- 26 hydraulic structures
- Signaling and safety equipment
The main quantities
- Landfill or landfill: 115,000 m3
- Loan for backfill: 105,000 m3
- Double-layer coating: 468,000 m2
- Gabions: 3,000 m3
- Piles Ø 1000: 12 units