Deviation from Route RN 17 at the dam reservoir on Oued Kebir

Deviation from Route RN 17 at the dam reservoir on Oued Kebir

Project

Deviation from Route RN 17 at the reservoir of the Dam on the Oued Kebir in the Region of Tabarka - Ain Drahem CH.434

  • Contract amount: 8 838 894.208 TND
  • Work completion time: 600 days
  • Client: Ministry of Agriculture, Environment and Water Resources

Consistency of the work

This project includes all the work to divert the RN 17 road and re-establish the tracks at the dam on Oued Kebir over a length of 11,120 km of road and 6,188 km of track

  • Clearance of rights-of-way
  • Earthworks
  • Pavement
  • Drainage
  • Deviation from dealer networks
  • 61 hydraulic structures, single, double and multiple gutters
  • Signaling and safety equipment

The main quantities

  • Landfill or landfill: 338,300 m3
  • Loan for backfill: 285,000 m3
  • Bituminous concrete: 16,500 tonnes
  • Gabions: 5,000 m3
  • Tree felling and stumping: 2,870 units