- Contract amount: 46 135 259.605 TND
- Work execution time: 30 months
- Client: Tunisie Autoroute
Consistency of the work
It is all the works necessary for the realization of the Maghrebian motorway M'saken el Jem section (Lot n ° 2), in particular the earthworks, works of art, pavements, drainage, equipment, signage, etc…. over a total length of the route of 22,800Km and of which: 1 Exchanger 28 Hydraulic works 14 Structures including 1 structure on a deep foundation (piles drilled with mud)
The main quantities
Landfill or landfill: 1,450,000 m3 Loan for backfill: 2,100,000 m3 Gravel bitumen: 76,000 m3 Bituminous concrete: 27,600 m3 Concrete: 37,440 m3 Concrete reinforcement: 3,690,000 Kg
- Montant du marché : 46 135 259.605 TND
- Délais d’exécution des travaux : 30 mois
- Maître de l’ouvrage : Tunisie Autoroute
Consistance des travaux
C’est l’ensemble des travaux nécessaires à la réalisation de l’autoroute Maghrébine tronçon M’saken el Jem (Lot n° 2), notamment les terrassements, ouvrages d’arts, chaussées, drainage, équipements, signalisation, etc….sur une longueur totale du tracé de 22.800Km et dont :
- 1 Echangeur
- 28 Ouvrages hydrauliques
- 14 Ouvrages d’art dont 1 ouvrage sur fondation profonde (pieux forés à la boue)
Les principales quantités
- Déblais mis en dépôt ou en remblais : 1 450 000 m3
- Emprunt pour remblais : 2 100 000 m3
- Grave bitume : 76 000 m3
- Béton bitumineux : 27 600 m3
- Béton : 37 440 m3
- Armature à béton : 3 690 000 Kg