Project
Redevelopment of specialized posts at the Port of Rades
Construction of the CH.911 multi-bulk dock
- Contract amount: 16 517 549,401 TND
- Work execution time: 12 months
- Client: Office of the Merchant Navy and Ports
Consistency of the work
Construction of a quay on beaten metal piles type HZ, crowned by prefabricated reinforced concrete beams and a solid slab, it represents a docking length of 200 ml, the quay connects to the solid earth which has a land area of 37,000 m2.
The wharf construction works include:
- the mud cleaning at - 12.00 hydro
- excavation at - 12.00 hydro
- demolition of old buildings and port infrastructure
- driving metal piles
- sheet pile wall
- realization of the full earth
- anti-corrosion painting of piles and sheet piles
- roads and various networks linked to solid ground
- lighting of open areas (4 poles of 21 m)
- wharf gear (80 t steel bollards, fenders, ladder)
- cathodic protection in soluble anodes
The main quantities
- Demolition of the albacore dukes (-1.50 to -12.00 hydro): 2,016 m3
- Metal piles in HZ profiles: 2,400 tonnes
- Sheet piles: 140 tons
- Concrete: 5,500 m3
- Concrete steels: 1,000,000 kg
- Bottom cleaning: 18,000 m3
- Excavation of the bottom of the quay: 22,000 m3
- 0.1 to 0.5 ton rip-rap: 87,000 tons
- Landfill or landfill: 16,500 m3
- Borrow materials: 40,500 m3
- Anti-corrosion paint: 5,000 m2