- Contract amount: 5,000,000,000 TND
- Work completion time: 360 days
- Client: Construction Committee of the Great Mosque of Carthag
Consistency of the work
It is a reinforced concrete structure calculated in compliance with the earthquake-resistant construction provisions (> 300 kg / m3), made up of posts carrying cover slabs from which are suspended single, double or triple arches made of reinforced concrete. and sunk in several levees.