BASMA training, rehabilitation and leisure club

BASMA training, rehabilitation and leisure club



Contract amount: 7,000,000,000 TND
Work completion time: 540 days
Client: BASMA Association for the Promotion of the Employment of the Disabled
 

Consistency of the work

Construction of a center for a rehabilitation and leisure training club for the disabled, and in particular the work of: 

Earthworks
Foundations
Reinforced concrete
Various concrete
Masonry
Plasters
Various common coverings (window sills - whistles - thresholds - etc.)
Insulations and expansion joints
Sealing
Installation of frames and pre-frames in wood, aluminum, and metal
Miscellaneous development - roads and VRD
Sewage networks.

The main quantities

Times (all depths 0 to 6 ml): 8,245 m3
Embankments: 14,050 m3
Concrete: 10,000 m3
Masonry: 14,370 m2
Flooring: 11,500 m2
Wall covering: 3,200 m2