RADES THERMAL PLANT

RADES THERMAL PLANT

Project 

Rades Thermal Power Plant Stage B

Contract amount: 22,559,752,191 TND
Work execution time: 36 months
Client: Tunisian Electricity and Gas Company "STEG"

 

Consistency of the work

Construction of a thermal power station, the work is based on deep foundations (driven piles of reinforced concrete section 45 x 45 cm.)

The works include the realization of the following works:

- Engine room
- 2 groups tables with a reinforced concrete slab floor with a thickness = 2.64 ml supported on BA poles
- Electrical building
- Boiler
- Pumping station (reinforced concrete slab poured under water)
- Compressor room
- Diesel room
- Store
- Rejection channel
- Diesel tank
- VRD
- Chimney height 102 ml, in poured reinforced concrete with sliding formwork and clad with refractory brick

 

The main quantities

Concrete: 35,500 m3
Steels: 4,750,000 kg
Driven piles: 2,236 units, unit length 22 ml