Travaux de Réhabilitation, de réaménagement et de protection du port de pêche de MAHDIA

Travaux de Réhabilitation, de réaménagement et de protection du port de pêche de MAHDIA

Project

Rehabilitation, redevelopment and protection works of the fishing port of MAHDIA CH.521

  • Contract amount: 43 455 040.270 TND
  • Work execution time: 36 Months
  • Client: Ministry of Agriculture-DGPA
  • Progress works : 12 %

Consistency of the work

All the work consists of a single lot divided into three sub-lots:

1 / Sub-lot N ° 1:

INFRASTRUCTURES (maintenance dredging of basins - main dyke - new block docks - rehabilitation of docks in basin 3 to -3.0Hdro - rehabilitation of the dock - repair of block docks - extension and development of embankments - repair of roadways existing)
1 / Sub-lot N ° 2:

Various networks
1 / Sub-lot N ° 3:

Superstructures